Local councillors and stakeholders have been informed that the planned date for a full (two-way) reopening of Gipsy Patch Lane has been brought forward by three months. Project managers at South Gloucestershire Council say they are now aiming to fully reopen the road from the end of September 2022.
Continue readingTag: MetroBus
Relief as Gipsy Patch bridge route reopens to traffic
The through-route along Gipsy Patch Lane between Little Stoke and the A38 Gloucester Road has finally reopened, albeit in one direction only, following a road closure that lasted 10 months longer than originally planned. The road was closed at the railway bridge site on 6th March 2020 to permit demolition of the old narrow brick-built bridge…
Continue readingRemodelled bus stops now in use at Parkway
New and remodelled bus stops have been brought into use at Bristol Parkway railway station as a £650k scheme of improvements to bus/rail interchange facilities nears completion. The project has seen upgrades to two existing bus stops and the installation of two new MetroBus-specification stops.
Continue readingGipsy Patch Lane to reopen one-way (westbound only) from Monday
South Gloucestershire Council has announced that Gipsy Patch Lane will reopen to traffic in a westbound direction only (towards the A38) from 6am on Monday 6th September 2021. The one-way system will operate between the Little Stoke Lane junction and the mini-roundabout at Rolls-Royce.
Continue readingScope of Gipsy Patch Lane road closure to be temporarily extended
A full closure of Gipsy Patch Lane between its junction with Little Stoke Lane and the railway bridge is scheduled to come into effect from 8pm tonight (Friday 27th August 2021). The temporary road closure is required to allow preparations to be made for the planned one-way (westbound) reopening of the road…
Continue readingRoad under Gipsy Patch Lane bridge to be tarmacked from Tuesday
Part of the road surface under the new Gipsy Patch Lane railway bridge is to be tarmacked in the coming week (w/c 9th August 2021) in preparation for the planned one-way (westbound-only) reopening of Gipsy Patch Lane in September.
Continue readingCouncil confirms one-way reopening of Gipsy Patch Lane “in September”
Gipsy Patch Lane, which has been closed to motor vehicles at the railway bridge for 16 months, is to be partially reopened “in September [2021]”, South Gloucestershire Council has announced. A drop-in public information event will take place in the car park of Stokers public house on Wednesday 4th August.
Continue readingRoad closure blocks direct access to Little Stoke shops from Gipsy Patch Lane
The closure of the straight stretch of Gifford Crescent leading directly off Gipsy Patch Lane from Monday 5th July 2021 means that motorists travelling from the east are now required to follow a diversion in order to reach the Little Stoke shops and post office.
Continue readingGifford Crescent to Gipsy Patch link due to be closed from Monday (5th July)
The latest temporary road closure associated with the Cribbs Patchway MetroBus Extension construction work is due to come into force in Little Stoke on Monday (5th July 2021), when the straight stretch of Gifford Crescent (directly off Gipsy Patch Lane) will be closed to motor vehicles.
Continue readingGipsy Patch Lane: Highway works intensify east of railway bridge
Following the frustrating news revealed in our May magazine that the railway bridge at Gipsy Patch Lane may not reopen to motorised traffic until December (and then only one way), the last month has seen a slew of announcements relating to highway works east of the bridge.